Stirling Hotel

Project Details

Client:

  • RAA

Site:

  • Stirling Hotel

 

Scope of Works

  • Surface mounted electrical infrastructure mounted in under ground car park area, enclosed in conduit and mounted on cable tray
  • Three 7kw AC Jetcharge EV units were installed on car park bay walls, providing convenient access for EV owners to charge their vehicles, while spending time at the hotel
  • A new dedicated EV distribution board was installed to manage the electrical supply and distribution specifically for the EV charging units
  • BCE&CJ Electrical handled the installation of sub mains, additional electrical supply lines, to support the EV charging infrastructure
  • A communications link was established to ensure proper connectivity and communication between the EV units and monitoring systems
  • BCE&CJ Electrical ensured proper line marking and signage to clearly indicate the designated parking and charging areas for EVS
  • The installed EV units were commissioned, tested, and integrated with Chargefox, ensuring their proper functioning. Handover processes were completed to transfer the project to RAA. By completing this installation project, BCE&CJ Electrical has contributed to the expansion of EV charging infrastructure and sustainable practices at Stirling Hotel